Sep 23, 2022 | Amanda Ross | 1057 views
MSC Construction
Message from MSC:
The South driveway will remain closed this weekend. Weare hoping to have it filled, packed and open Monday the 26th. We will continue to keep the barricades at the end of that driveway preventing access and all vehicles entering and exiting the facility will have to be done through the north driveway as there is a trench dug across the south entrance from the building to our transformer. This area will continue to be fenced off, with no access to the east side vestibule or the exit door by the men’s bathroom. Staff will assure the rink 2 rear door is unlocked for access as well as the front west side. The main issue remains with having to walk over the curb to cut through the lawn, so there is a possibility it is not accessible for all.